Oil and Gas Facilities Automation Projects
Scope: Mangan Inc. provided all necessary services for the replacement of a combination of pneumatic controllers, Ronan panels and legacy PLCs (72 different manufacturers, models or versions) with a new Siemens PCS7 hybrid control system. This project included five oil and gas production facilities (four offshore and one onshore) and involved the design, installation and hot cutover of approximately 25,000 loops. Mangan Inc. successfully completed this lump sum EPC project in 2004 on schedule and budget, with less than 2% change orders.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Sulfur Plant CEMS Analyzers
Scope: Engineer, design and fabricate three (3) Continuous Emissions Monitoring Systems, program PLCs, establish fiber optic communications with associated alarms and operator interface.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Ground Level Monitoring System
Scope: Design wireless communications network for six (6) hydrocarbon analyzers and three (3) weather stations in remote locations.
|
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Critical Lab Equipment Monitoring Systems (CLEMS) Design
Scope: Engineer, design and fabricate 4 PLC panels for monitoring lab equipment with associated reporting and alarming.
|
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Octane Engine Upgrade Engineering
Scope: Replace obsolete COMOC system with Falling Level Octane Analyzer. eplace points that interface with BRC/BPC and reconfigure AM program. Automate Certification report to be generated by Honeywell TDC system using a CLX Processor to extract and pass data from the Falling level computer to Honeywell via a PLCG.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Offshore Historian Installation
Scope: Install new historian systems on two (2) oil and gas offshore production platforms. Design and install corporate historian network and associated firewalls for communications and remote system management.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
[back to top]
|
 |
|
| |
| |
| |
 |
Refinery Steam Plant Modernization
Scope: Replace obsolete steam plant and precipitator control room and associated equipment, add safety interlocks for cat cracker and boiler, and modify precipitator controls and safety interlocks.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Oil Production Facilities Automation Project
Scope: Replacement and upgrade of (5) production site's control systems (700 wells and related processing systems) with a new hybrid based instrument, safety, automation and information system infrastructure.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery Cogen Emissions Monitoring Upgrade
Scope: Replace aging emissions monitoring systems on 4 Cogen Trains, ncluding associated plant and regulatory data acquisition systems.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Pipeline Delivery & Stubline Automation
Scope: Replacement of obsolete terminal and stubline control systems with new PLC based controls, local HMI and satellite communication to Central SCADA Master.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery FCC Main Air Blower Modernization
Scope: Concurrent with an MAB Mechanical Upgrade, replace all local control and instrumentation with a new pre-fabricated Local Panel with equipment safety, speed, anti-surge, vibration, logic and process controllers, local HMI and remote control and indication.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Biotech Mfg Building Control System Upgrade Project
Scope: Install and commission a new HMI and SQL Server database Statistical Process Control System.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Pipeline Terminals Upgrade
Scope: Replacement of obsolete control hardware with new PLC/HMI based systems for Pipeline Delivery Station and Truck Terminal Control Systems.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
[back to top]
|
 |
|
|
|
 |
| |
| |
 |
Refinery Clean Fuels & FCC Upgrades
Scope: Modifications to a number of existing refinery units, with associated and selective upgrade to the plant safety, DCS and PLC based control systems.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery In Line Blender
Scope: Replacement of existing refinery blender systems with new NIR Analyzer based automatic blenders, on a new DCS, and w/ interface to existing tank gauging systems.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Oil Production Facilities Automation FEL
Scope: Development of front end loading deliverables, including a menu of options, for a facility wide instrument, safety, automation and historian upgrade.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Pipeline Stubline Automation
Scope: As a continuing phase of a system wide automation project, replacement of obsolete terminal and stubline control systems with new PLC based controls, local HMI and satellite communication to Central SCADA Master
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Gas Storage & Transmission Facility CEMS
Scope: Replace predictive emissions monitoring systems with 5 new continuous extractive analyzer based emissions monitoring systems with regulatory and plant data acquisition systems.
|
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Biotech Mfg Building Lyophilizer Project
Scope: Install new Manufacturing Control System for a new lab and process design facility in a biotech plant.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Pipeline Regional SCADA Upgrade
Scope: Replacement of existing obsolete control systems and instrumentation for 12 pipeline stations, with new state of the art hardware.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
[back to top]
|
 |
|
|
 |
| |
| |
 |
Pipeline Automation
Scope: As a continuing phase of a system wide automation project, replacement of existing obsolete control systems with new state of the art hardware, and installation of modular software that initiates standardized O&M practices.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Chemical Plant Electrical Modernization
Scope: Replace obsolete medium and low voltage power distribution systems to improve plant reliability.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery Carbon Plant Modernization
Scope: Reinstrumentation of a refinery carbon plant, including replacement of existing control systems hot.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Chemical Plant Blender Modernization
Scope: Installation of new blend manifold and control systems, replacing manually operated blend operations with a new automated batch control system.
|
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Chemical Plant Automation
Scope: Reinstrumentation of a chemical plant, including replacement of existing control systems hot, with new batch control system on a hybrid control platform.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery Crude Unit CEMS NOx Reduction and Safety Systems
Scope: For BAAQMD Nox Rule compliance, install 4 new CEMS, with plant safety systems for adjacent refinery units.
|
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Specialty Chemical Enterprise Wide Historian Installations
Scope: Installation of plant historians on 6 specialty chemical plants throughout the country, with intranet based communication to company headquarters.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
[back to top]
|
 |
 |
| |
| |
 |
Pipeline Prototype Automation Project Scope: Prototype development, installation and commissioning of a new standardized and modular control system for a pipeline automation system upgrade program.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinerywide Product Blender Analytical System
Scope: Installation of process analyzers at process units and pre & post blend manifolds, and the installation of a refinerywide process SCADA as a part of a Clean Fuels Projects.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery CEMS DAS Replacement
Scope: Replace failing CEMS data acquisition system, resident on top of a refinery-wide emissions monitoring network, communicating continuously to refinery process and information systems, and daily to local agencies.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery Crude Unit Reinstrumentation
Scope: Reinstrumentation of a process unit, including replacement of existing control systems hot, and the rebuild of an old control room without interrupting plant operation.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery Boiler Feedwater Recycled Water Upgrades
Scope: Installation of new MF/RO off plot systems for Boiler Feedwater to an existing refinery distribution system.
|
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Biotech R&D Building Managment Systems
Scope: Install new Building Management System for an existing lab and process design facility in a biotech plant.
| |
|
|
|
|
|
|
|
|
|
|
|
| FEL |
PM |
E |
I |
P |
CM |
C |
Tr |
Te |
C/V |
S |
M |
Refinery Marine Terminal VRC Upgrade
Scope: Reverse engineer large VR SCADA to identify operational problems, simplify operating procedures, and reprogram systems to operate reliably.
| |
|
|
|
|
|
|
|
|
|
|
|